Hydro resumes bauxite pipeline operation in Brazil

On October 8, Hydro resumed operation of the pipeline transporting bauxite from Hydro Paragominas bauxite mine to the alumina refinery Alunorte in Brazil.

The pipeline at the Paragominas mine. (Photo: Hydro)

Production at Paragominas bauxite mine has started, and alumina production is now being ramped up at Hydro’s Alunorte alumina refinery.

Based on a technical assessment, Hydro halted operation of the pipeline for extended maintenance in August to replace a section of the pipeline earlier than scheduled.

During the extended maintenance period, production at Alunorte had been reduced to a level between 35-45 percent of full capacity to balance bauxite inventories.

Hydro Paragominas bauxite pipeline in Brazil halted for extended maintenance (Aug. 18, 2020)